Construction progress for all blocks as at the end of August 2012. Progress status updated bi-monthly. The next update will be in mid-November 2012. Click on thumbnail for full picture.

   
   
S/N
Items
Progress Status
1
Foundation Work
com
2
Reinforced Concrete Framework
com
3
Brick Walls
com
4
Ceilings
com
5
Doors and Windows Frames
com
6
Car Park, Roads and Drains
com
7
TOP Issued
prog