Construction progress for all blocks as at the end of April 2013. Progress status updated bi-monthly. The next update will be in mid-July 2013. Click on thumbnail for full picture.

   
     
S/N
Items
Progress Status
1
Foundation Work
prog
2
Reinforced Concrete Framework
prog
3
Brick Walls
com
4
Ceilings
com
5
Doors and Windows Frames
com
6
Car Park, Roads and Drains
com
7
TOP Issued
com Completed prog In Progress nil Nil
 
 
 